Subtitle: Nuclear power plants require long construction
schedules
Up until now, the Truth About Nuclear Power series has discussed
the costs of operating and constructing the plants, and the impact on scarce
water resources. It has been shown that
nuclear power plants cost far too much to construct, use far too much water,
cannot compete in today’s electricity market, and if they were the sole source
of electricity on a grid, power prices would escalate to unacceptably high
levels.
This article discusses one of the reasons nuclear plants cost
so much, and debunks one of the favorite talking points of the nuclear
advocates. The advocates are fond of
saying that nuclear plants would not cost so much if only the lawyers would
step aside and let the plants be built without lawsuits. In fact, frivolous lawsuits are now barred
for new nuclear power construction in the US.
However, costly delays are occurring, and will occur in the future for
the usual set of construction delay issues.
Delays cost money, and the longer the delay, the more money is spent by
one of the parties to the construction.
Examples of construction delays include, but are not limited
to, tearing out and re-working faulty construction, equipment suppliers
providing late or defective items, serious adverse weather, unforeseen site
conditions, and redesign for new NRC requirements. Also, delays can be caused by worker
slowdowns, lawsuits for allowable causes, owner-contractor disputes, faulty
design that requires corrections, acts of God or the enemy (force majeur),
improper scheduling by the contractor, inadequate workforce staffing or
untrained workforce (learning on the job), poor supervision, and others.
As one example, nuclear power plants have many critical welds. The critical welds must be performed by
qualified welders, who are paid a premium.
Also, the critical welds are required to be x-rayed to ensure the welds
meet quality control specifications and will be sufficiently strong. It takes time, and costs money to x-ray and
inspect all those critical welds. It is
well-known that the South Texas Nuclear Plant had many faulty critical welds
that failed x-ray inspection and had to be welded again until they were right.
Another example, again from the South Texas Nuclear Plant, of
faulty design that required correction is the mis-match on the drawings for two
halves of the plant. The piping and
other items that were to connect across the match-line were off by a noticeable
amount. The work was delayed while the
engineering firm re-engineered and re-issued the proper drawings. Delays caused by faulty rebar for concrete have
been an issue at the Vogtle plant under construction in Georgia, USA. Other delays at Vogtle include design changes,
and delivery of equipment. Vogtle is now reported to be 21 months behind schedule. That number will surely increase as more time passes. See link for
list of delays and cost over-runs at Vogtle.
Delays occur in other countries, also. As an example, the Finland plant being
installed by Areva had delays with the concrete. Apparently, the concrete was not to the
required specification. That project is also years behind schedule.
Even without delays, nuclear plants require longer to
construct due to the inherent danger of nuclear power (discussed in Part Five) and
the three levels of containment required by the NRC. In short, there are many more items of
equipment required to contain the deadly radioactivity if and when an accident
occurs. More items of equipment require longer
construction times. Also, more testing
is required before startup, more inspection as the construction progresses, all
of which take time.
Conclusion
Nuclear power plants require long construction schedules,
made longer by delays that have nothing to do with lawsuits to impede progress.
Previous articles in the Truth About
Nuclear Power series are found at the following links.
Additional articles will be linked as they are published.
Part One – Nuclear Power Plants Cannot Compete
Part Three – Nuclear Power Plants Cost Far Too Much to Construct
Part Four – Nuclear Power Plants Use Far More Fresh Water
Part Five – Cannot Simply Turn Off a
Nuclear Power Plant
Part Six – Nuclear Plants are Huge to Reduce Costs
Part Seven -- All Nuclear Grid Will Sell Less Power
Part Nine - this article
Part Ten - Nuclear Plants Require Costly Upgrades After 20 to 30 Years
Part Eleven - Following France in Nuclear Is Not The Way To Go
Part Twelve - Nuclear Plants Cannot Provide Cheap Power on Small Islands
Part Thirteen - Nuclear Plants Are Heavily Subsidized
Part Fourteen - A Few More Reasons Nuclear Cannot Compete
Part Fifteen - Nuclear Safety Compromised by Bending the Rules
Part Sixteen - Near Misses on Meltdowns Occur Every 3 Weeks
Part Seventeen - Storing Spent Fuel is Hazardous for Short or Long Term
Part Eighteen - Reprocessing Spent Fuel Is Not Safe
Part Thirteen - Nuclear Plants Are Heavily Subsidized
Part Fourteen - A Few More Reasons Nuclear Cannot Compete
Part Fifteen - Nuclear Safety Compromised by Bending the Rules
Part Sixteen - Near Misses on Meltdowns Occur Every 3 Weeks
Part Seventeen - Storing Spent Fuel is Hazardous for Short or Long Term
Part Eighteen - Reprocessing Spent Fuel Is Not Safe
Part Nineteen - Nuclear Radiation Injures People and Other Living Things
Part Twenty - Chernobyl Meltdown and Explosion
Part Twenty One - Three Mile Island Unit 2 Meltdown 1979
Part Twenty Two - Fukushima The Disaster That Could Not Happen
Part Twenty Three - San Onofre Shutdown Saga
Part Twenty Four - St. Lucie Ominous Tube Wear
Part Twenty - Chernobyl Meltdown and Explosion
Part Twenty One - Three Mile Island Unit 2 Meltdown 1979
Part Twenty Two - Fukushima The Disaster That Could Not Happen
Part Twenty Three - San Onofre Shutdown Saga
Part Twenty Four - St. Lucie Ominous Tube Wear
Part Twenty Five - Price-Anderson Act Protects Nuclear Plants Too Much
Part Twenty Six - Evacuation Plans Required at Nuclear Plants
Part Twenty Seven - Power From Nuclear Fusion
Part Twenty Eight - Thorium MSR No Better Than Uranium Process
Part Twenty Nine - High Temperature Gas Reactor Still A Dream
Part Thirty - Conclusion
Part Twenty Eight - Thorium MSR No Better Than Uranium Process
Part Twenty Nine - High Temperature Gas Reactor Still A Dream
Part Thirty - Conclusion
No comments:
Post a Comment