Showing posts with label Olkiluoto. Show all posts
Showing posts with label Olkiluoto. Show all posts

Saturday, October 14, 2017

Finland Nuclear Plant Fiasco

Subtitle:  Huge Delays and Cost Overrun are Nuclear's New Normal

The new nuclear plant in Finland at Olkiluoto, known as Olkiluoto 3, is finally nearing completion and perhaps a startup.   This is a 1600 MWe single-reactor, pressurized water design using the European Pressurized Reactor (EPR) by Areva, the French company.   If completed as now contemplated, the construction will have taken 14 years start to finish.  That's a big IF.   The cost has soared to almost triple the original amount, from €3.2 billion to  €8.5 billion.  In US terms, that is $10 billion for a cost/kW of $6,300.    One can be confident that the stated costs do not include interest on construction funds. 

UPDATE: 3-19-19, Finland issues operating license for the Olkiluoto plant, for anticipated startup in 2020.  That's 11 years later than the initial plan, and fifteen years start-to-finish, and cost is almost 3 times the original cost.   - - end update

The Financial Times article, "Nuclear plant nears completion after huge delays," has this to say:  see link

"Areva, the French reactor manufacturer, began building Olkiluoto in 2005 with a target for completion by 2009 at a cost of €3.2bn. The latest timetable would see it open almost a decade late at the end of 2018 and nearly three times over budget at €8.5bn.

The project is the most extreme example of the delays and cost overruns which have become commonplace in the nuclear industry, plunging reactor companies such as Areva and Toshiba’s Westinghouse subsidiary into financial crisis.


Areva’s ability to complete Olkiluoto over the next year and learn lessons from the fiasco as it presses ahead with similar projects in France and the UK will go a long way to determining the industry’s chances of recovery."


The financial impact of the long delays and huge costs is that power price that must be obtained is in the $120 per MWh range.  Of that, $80 is for capital recovery and $40 is for operating costs.   That presumes, of course, that the plant actually runs every year at an average of 90 percent of nameplate capacity.   If the output slips to just 85 percent, the power sales price must increase to $127-130 per MWh.  

Nuclear power via these new, supposedly safe and efficient plants is some of the most expensive power on the planet.   This EPR design is also under construction in France, and was selected in a twin-reactor design for the UK at Hinkley Point C.   

Meanwhile, electricity via offshore wind power, supplemented by onshore natural gas load-following plants, is far more cost-effective, much safer, and has zero chance of a reactor meltdown. 



Roger E. Sowell, Esq.
Marina del Rey, California
copyright (c) 2017 by Roger Sowell - all rights reserved


Topics and general links:

Nuclear Power Plants.......here
Climate Change................here  and here
Fresh Water......................here
Engineering......................here  and here
Free Speech.................... here
Renewable Energy...........here 

Sunday, October 12, 2014

UK Hinkley Point Nuclear Plant Heavily Subsidized

Subsidies for nuclear power plants are not just in the US.   This week, several sources report that UK's proposed Hinkley Point C plant, a 3,200 MWe nuclear plant, received a blessing from the EU Commission to obtain public funding - a form of subsidy.  See link for a BBC report.   (for more on US subsidies for its nuclear power plants, of which there are at least six different subsidies, see this link and this link). 

The Hinkley Point C plant will have two reactors, each 1,600 MWe, of the EPR reactor design that is currently such a fiasco in Finland at Olkiluoto. (see link)   To their credit, the BBC article admits the Hinkley Point C will require 10 years to first operation.  However, the plant life is also stated as 60 years, which is wildly optimistic. 

The subsidy for Hinkley Point C apparently takes the form of a high sales price for power at the transaction bar - the plant boundary.  The plant owner is guaranteed the equivalent of US 15 cents per kWh, approximately double the present rate for wholesale power in the UK.  

What is interesting is the quoted price to build the plant, at £24.5 billion (the equivalent of US$ 39.2 billion).   This equates to MORE than $10,000 per kW, at $12,250.   Again, this is precisely what SLB has maintained all along - a new nuclear power plant costs far more than the $4,000 some advocates maintain.  Instead, it will cost at least $10,000 per kW, and more likely $12,000 per kW.   Here we see at least a small beginning of honesty from the nuclear establishment.  

However, given the long, dismal history of nuclear plant schedule delays and cost overruns, it is to be expected that the Hinkley Point C twin reactor plant will take far longer than 10 years to startup, and will cost far more than US$ 39 billion.  It will likely require 15 years or longer, and $48 billion or even more.  

The poor people of the UK will foot the bill, as they have few choices but to buy the power.  However, with the higher and higher prices that will inevitably occur, it may be possible for some of the grid customers to unplug themselves from the grid.  There may be better, cheaper ways to produce their own electricity.  For an analysis of such ways, see this link.   In the year 2023 or perhaps later, 2030 as a more realistic startup date, the options for unplugging from the grid and self-generation will likely be more numerous and more appealing than what we have today.  

It will be a long, long time before Hinkley Point C begins producing power and its true impact will be felt.  One can only hope the resourceful people of the UK will rise to the occasion and replace as much power as possible to self-generate and save money.  

In another moment of rare candor, UK officials tried to justify the new nuclear plant by stating that there are few options available for providing reliable power.  They state that coal is nearly exhausted and would be unreliable if imported, natural gas also is in short supply and in danger of being cut off by selling nations (meaning Russia), and wind is too unreliable.  Solar in the UK area is not at all economically attractive, owing to the high latitude and cloudy weather.  (The UK, after all, is of the same approximate latitude as Hudson Bay in Canada)   

What, then, is left but nuclear?    One answer, of course, is offshore wind coupled to ocean-based storage systems that supply power on demand, quite reliably. (see link) By 2030, one expects that the offshore wind with storage to be well-proven and very attractive.    All the offshore wind projects must do to compete is beat US$12,250 per kW.  The energy is free, and many of the other very high costs of running a nuclear plant simply do not exist for wind-energy. 

Update - 10/13/2014:  UK wind resources offshore are quite good.  see link   -- end update. 



Roger E. Sowell, Esq. 
Marina del Rey, California

copyright (c) 2014 by Roger Sowell -- all rights reserved

Monday, September 1, 2014

Finland Nuclear Plant Delayed Yet Again

Subtitle: Four Year Construction Time More Than Tripled

The 1,600 MWe nuclear power plant under construction in Olkiluoto, Finland, is now delayed so much that first power production is not expected until sometime in 2018.  That is 9 years later than the original schedule, with a 13 year project construction time.  See link to the Finnish utility's website, TVO, and the announcement.  

This is yet more evidence that the nuclear power industry cannot deliver what they promise: the plant is not only years and years behind schedule, it is billions of Euros over budget.  

This plant has been the subject of previous SLB articles, see here, here, here, and here

This plant is designed for 1,600 MWe output, in an attempt to attain lower costs from economy of scale.  Larger plants can have lower production costs, and in many industries these economies are achieved.   But, with nuclear power plants, this does not seem to be the case.  Any economy of scale is surely obliterated by the increased financing costs on construction loans over a 13 year (2018-2005) construction period, plus escalations from inflation for materials, services, and labor.   These concepts are explored in some detail in Part Six of Truth About Nuclear Power (see link). 

The truth about the Finland reactor is that four more years are required, at least are now estimated as required, before startup.  Four years is a long time, and many more mistakes and problems can occur.  The plant may very well not see first production in 2018, but will likely be delayed much more.  

The reality is that, even after 50 years or more of design, development, actual experience, fine-tuning, and making best efforts around the world, nuclear power (as of 2011 per EIA statistics, see TANP part 11) provides only 11.7 percent of all power world-wide.   The only technologies smaller than nuclear’s share are oil (4.8 percent) and a catch-all category (4.5 percent) that includes wind, solar, geothermal, and various other renewable power.   One would expect that nuclear, if it were truly a superior technology economically and safe, would have easily surpassed coal, natural gas, and hydroelectric power (41, 22, and 16 percent approximately, respectively).

Roger E. Sowell, Esq. 
Marina del Rey, California

Copyright (c) 2014 by Roger Sowell  -- All rights reserved